If wheat requires about 7.5 cm of water after every 28 days, and base period for wheat is 140 days,then value of delta for wheat will be :
A.
37.5 cm
B.
47.5 cm
C.
57.5 cm
D.
7.5 cm
Right Answer is :
✓ A. 37.5 cm
⚑ Report
Views 👍 :2.0K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ If base period for a particular crop ...
➣ What is the evaporation, if 4.75 litre ...
➣ On suitable foundation, the earthen dam can ...
➣ According to Lacey, the depth of scour ...
➣ The statement "ordinate of the direct runoff ...
➣ The meander belt for an alluvial stream ...
➣ The based period of a 6 h ...
➣ An irrigation canal is to be designed ...
➣ In gravity dam, the main overturning force ...
➣ If intensity of rainfall is more than ...
❖ Take a qick MCQ Test on
➤ Solid Waste and Waste Water Treatment
➤ Concrete Structure
➤ Steel Structure
➤ Pollution (Air and Noise)
➤ Water Supply
➤ Soil Mechanics and Foundation
➤ Concrete Technology
➤ Miscellaneous