The meander belt for an alluvial stream ...
Que.
The meander belt for an alluvial stream is estimate to be 9 km. The peak discharge in this river will roughly be the order of :
A.
40.60 cumecs
B.
16.00 cumecs
C.
13.77 cumecs
D.
18.89 cumecs
Right Answer is :
✓ C. 13.77 cumecs
⚑ Report
Views 👍 :1.1K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Delta for a crop when its duty ...
➣ "Specific yield" for an unconfined aquifer is ...
➣ If wind velocity at a height of ...
➣ If one cumec of water is pumped ...
➣ An undisturbed rock sample has on oven ...
➣ What is the evaporation, if 4.75 litre ...
➣ The statement "ordinate of the direct runoff ...
➣ If wheat requires about 7.5 cm of ...
➣ The based period of a 6 h ...
➣ If a river in an alluvial plain ...
❖ Take a qick MCQ Test on
➤ Pollution (Air and Noise)
➤ Surveying
➤ Concrete Technology
➤ Fluid Mechanics and Hydraulics
➤ Concrete Structure
➤ Miscellaneous
➤ Soil Mechanics and Foundation
➤ Building Material