An irrigation canal is to be designed ...
Que.
An irrigation canal is to be designed to deliver 8.3 cumecs to meet the peak Rabi demand of a total of 8000 hectares of cropped area. The estimated canal losses are 25 % of the head discharge . The duty an capacity of this will be :
A.
723.32 ha/cumecs
B.
800 ha/cumecs
C.
594.64 ha/cumecs
D.
694.34 ha/cumecs
Right Answer is :
✓ A. 723.32 ha/cumecs
⚑ Report
Views 👍 :4.1K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ What volume is represented by 57mm of ...
➣ What is the evaporation, if 4.75 litre ...
➣ The area, on which crops are growing ...
➣ A well with a radius of 0.5 ...
➣ If electrical conductivity of water is in ...
➣ The value of Sodium Absorption Ratio for ...
➣ What is the evaporation, if 4.75 litre ...
➣ The based period of a 6 h ...
➣ What is the evaporation, if 4.75 litre ...
➣ If a tengent drawn parallel to the ...
❖ Take a qick MCQ Test on
➤ Hydrology
➤ Fluid Mechanics and Hydraulics
➤ Solid Waste and Waste Water Treatment
➤ Strength of Material
➤ Surveying
➤ Steel Structure
➤ Concrete Structure
➤ Irrigation