Que.
An irrigation canal is to be designed to deliver 8.3 cumecs to meet the peak Rabi demand of a total of 8000 hectares of cropped area. The estimated canal losses are 25 % of the head discharge . The duty an capacity of this will be :
A.
723.32 ha/cumecs
B.
800 ha/cumecs
C.
594.64 ha/cumecs
D.
694.34 ha/cumecs
Right Answer is :
✓ A. 723.32 ha/cumecs
⚑ Report
Views 👍 :3.3K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Delta for a crop when its duty ...
➣ If co-efficient of veriation of rainfall values ...
➣ An undisturbed rock sample has on oven ...
➣ If a tengent drawn parallel to the ...
➣ The area, on which crops are growing ...
➣ The based period of a 6 h ...
➣ Out of 150 cm of water pumped ...
➣ A well with a radius of 0.5 ...
➣ If wheat requires about 7.5 cm of ...
➣ If intensity of rainfall is more than ...
❖ Take a qick MCQ Test on
➤ Miscellaneous
➤ Hydrology
➤ Building Material
➤ Steel Structure
➤ Transportation Engineering
➤ Irrigation
➤ Water Supply
➤ Solid Waste and Waste Water Treatment