An irrigation canal is to be designed ...
Que.
An irrigation canal is to be designed to deliver 8.3 cumecs to meet the peak Rabi demand of a total of 8000 hectares of cropped area. The estimated canal losses are 25 % of the head discharge . The duty an capacity of this will be :
A.
723.32 ha/cumecs
B.
800 ha/cumecs
C.
594.64 ha/cumecs
D.
694.34 ha/cumecs
Right Answer is :
✓ A. 723.32 ha/cumecs
⚑ Report
Views 👍 :4.1K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ If a river in an alluvial plain ...
➣ If a tengent drawn parallel to the ...
➣ The value of Sodium Absorption Ratio for ...
➣ If wheat requires about 7.5 cm of ...
➣ Delta for a crop when its duty ...
➣ In India, which of the following is ...
➣ If base period for a particular crop ...
➣ "Specific yield" for an unconfined aquifer is ...
➣ A well with a radius of 0.5 ...
➣ If one cumec of water is pumped ...
❖ Take a qick MCQ Test on
➤ Concrete Structure
➤ Soil Mechanics and Foundation
➤ Strength of Material
➤ Irrigation
➤ Pollution (Air and Noise)
➤ Concrete Technology
➤ Solid Waste and Waste Water Treatment
➤ Fluid Mechanics and Hydraulics