An irrigation canal is to be designed ...
Que.
An irrigation canal is to be designed to deliver 8.3 cumecs to meet the peak Rabi demand of a total of 8000 hectares of cropped area. The estimated canal losses are 25 % of the head discharge . The duty an capacity of this will be :
A.
723.32 ha/cumecs
B.
800 ha/cumecs
C.
594.64 ha/cumecs
D.
694.34 ha/cumecs
Right Answer is :
✓ A. 723.32 ha/cumecs
⚑ Report
Views 👍 :4.1K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ If intensity of rainfall is more than ...
➣ If one cumec of water is pumped ...
➣ If the area of catchment is 567 ...
➣ What is the evaporation, if 4.75 litre ...
➣ The meander belt for an alluvial stream ...
➣ If co-efficient of veriation of rainfall values ...
➣ If electrical conductivity of water is in ...
➣ Delta for a crop when its duty ...
➣ According to Lacey, the depth of scour ...
➣ The 6000 hectares of gross commanded area ...
❖ Take a qick MCQ Test on
➤ Strength of Material
➤ Building Material
➤ Transportation Engineering
➤ Pollution (Air and Noise)
➤ Concrete Technology
➤ Miscellaneous
➤ Hydrology
➤ Steel Structure