An irrigation canal is to be designed ...
Que.
An irrigation canal is to be designed to deliver 8.3 cumecs to meet the peak Rabi demand of a total of 8000 hectares of cropped area. The estimated canal losses are 25 % of the head discharge . The duty an capacity of this will be :
A.
723.32 ha/cumecs
B.
800 ha/cumecs
C.
594.64 ha/cumecs
D.
694.34 ha/cumecs
Right Answer is :
✓ A. 723.32 ha/cumecs
⚑ Report
Views 👍 :2.6K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Delta for a crop when its duty ...
➣ If electrical conductivity of water is in ...
➣ What is the evaporation, if 4.75 litre ...
➣ If a tengent drawn parallel to the ...
➣ What is the evaporation, if 4.75 litre ...
➣ The meander belt for an alluvial stream ...
➣ What volume is represented by 57mm of ...
➣ What is the evaporation, if 4.75 litre ...
➣ On suitable foundation, the earthen dam can ...
➣ The 6000 hectares of gross commanded area ...
❖ Take a qick MCQ Test on
➤ Concrete Technology
➤ Steel Structure
➤ Miscellaneous
➤ Surveying
➤ Concrete Structure
➤ Building Material
➤ Strength of Material
➤ Pollution (Air and Noise)