An irrigation canal is to be designed ...
Que.
An irrigation canal is to be designed to deliver 8.3 cumecs to meet the peak Rabi demand of a total of 8000 hectares of cropped area. The estimated canal losses are 25 % of the head discharge . The duty an capacity of this will be :
A.
723.32 ha/cumecs
B.
800 ha/cumecs
C.
594.64 ha/cumecs
D.
694.34 ha/cumecs
Right Answer is :
✓ A. 723.32 ha/cumecs
⚑ Report
Views 👍 :3.0K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ If base period for a particular crop ...
➣ An irrigation canal is to be designed ...
➣ The statement "ordinate of the direct runoff ...
➣ What is the evaporation, if 4.75 litre ...
➣ What volume is represented by 57mm of ...
➣ The 6000 hectares of gross commanded area ...
➣ What is the evaporation, if 4.75 litre ...
➣ If a river in an alluvial plain ...
➣ Out of 150 cm of water pumped ...
➣ A well with a radius of 0.5 ...
❖ Take a qick MCQ Test on
➤ Hydrology
➤ Building Material
➤ Pollution (Air and Noise)
➤ Transportation Engineering
➤ Concrete Structure
➤ Concrete Technology
➤ Miscellaneous
➤ Solid Waste and Waste Water Treatment