Que.
The maximum efficiency of BOD removal is achieved in :
A.
oxidation pond
B.
oxidation ditch
C.
aerated lagoons
D.
trickling filters
Right Answer is :
✓ B. oxidation ditch
⚑ Report
Views 👍 :1.8K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ In which type of lakes, does a ...
➣ which of the following sewage treatment methods ...
➣ Sludge volume index is defined as the ...
➣ Sewage treatment units are designed for : ...
➣ What is the most common causes of ...
➣ Which of the following units works in ...
➣ In which treatment unit is "Schmutz decke" ...
➣ When there is no recirculation of sewage, ...
➣ Which of the following treatment processes are ...
➣ Following reactions take place during anareobic digestion ...
❖ Take a qick MCQ Test on
➤ Soil Mechanics and Foundation
➤ Pollution (Air and Noise)
➤ Transportation Engineering
➤ Irrigation
➤ Building Material
➤ Water Supply
➤ Miscellaneous
➤ Concrete Technology