The maximum efficiency of BOD removal is ...
Que.
The maximum efficiency of BOD removal is achieved in :
A.
oxidation pond
B.
oxidation ditch
C.
aerated lagoons
D.
trickling filters
Right Answer is :
✓ B. oxidation ditch
⚑ Report
Views 👍 :1.5K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Critical factors for the activated sludge treatment ...
➣ Sewage treatment units are designed for : ...
➣ The ratio of 5 days BOD to ...
➣ Which of the following treatment processes are ...
➣ 'Air binding' may occur in : ...
➣ Total volatile suspended solids to be anaerobically ...
➣ In the design of grit chambers : ...
➣ Are requirements (ha) for disposal of the ...
➣ The trickling filter is designed to remove: ...
➣ The unit in which both sedimentation and ...
❖ Take a qick MCQ Test on
➤ Solid Waste and Waste Water Treatment
➤ Soil Mechanics and Foundation
➤ Pollution (Air and Noise)
➤ Surveying
➤ Transportation Engineering
➤ Building Material
➤ Water Supply
➤ Irrigation