The maximum efficiency of BOD removal is ...
Que.
The maximum efficiency of BOD removal is achieved in :
A.
oxidation pond
B.
oxidation ditch
C.
aerated lagoons
D.
trickling filters
Right Answer is :
✓ B. oxidation ditch
⚑ Report
Views 👍 :1.6K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Are requirements (ha) for disposal of the ...
➣ The effect of increasing diameters of sewer ...
➣ The characteristics of fresh and septic sewage ...
➣ The biochemical treatment of sewage effluents is ...
➣ Which of the following terms, correctly describes ...
➣ The two main gases liberated from an ...
➣ Which one the following units is employed ...
➣ 'Air binding' may occur in : ...
➣ After which of the following water treatment ...
➣ which of the following sewage treatment methods ...
❖ Take a qick MCQ Test on
➤ Concrete Technology
➤ Hydrology
➤ Concrete Structure
➤ Surveying
➤ Strength of Material
➤ Water Supply
➤ Pollution (Air and Noise)
➤ Soil Mechanics and Foundation