The maximum efficiency of BOD removal is ...
Que.
The maximum efficiency of BOD removal is achieved in :
A.
oxidation pond
B.
oxidation ditch
C.
aerated lagoons
D.
trickling filters
Right Answer is :
✓ B. oxidation ditch
⚑ Report
Views 👍 :1.6K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Total volatile suspended solids to be anaerobically ...
➣ The biochemical treatment of sewage effluents is ...
➣ Which of the following are claimed as ...
➣ Are requirements (ha) for disposal of the ...
➣ BOD is preferred to COD as an ...
➣ Ventilation of sewer lines is necessary to ...
➣ In facultative stabilization pond, the sewage is ...
➣ Which of the following pairs is not ...
➣ The ratio of 5 days BOD to ...
➣ The correct relation between theoretical oxygen demand ...
❖ Take a qick MCQ Test on
➤ Solid Waste and Waste Water Treatment
➤ Concrete Technology
➤ Fluid Mechanics and Hydraulics
➤ Soil Mechanics and Foundation
➤ Surveying
➤ Concrete Structure
➤ Steel Structure
➤ Building Material