Que.
Important points selected at the ends of the chain lines to command the boundaries of the survey are called :
A.
Main stations
B.
Subsidiary stations
C.
Tie stations
D.
None of the above
Right Answer is :
✓ A. Main stations
⚑ Report
Views 👍 :1.5K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ With regards to traversing : ...
➣ In which of the following types of ...
➣ What is the psychological widening of pavement ...
➣ Errors which remain after mistakes and systematic ...
➣ The optical square is based on the ...
➣ If free mean speed on a roadway ...
➣ Limiting length of offset depends upon : ...
➣ Which of the following is taken into ...
➣ Length of summit curve for a stopping ...
➣ Length of transition curve for design speed ...
❖ Take a qick MCQ Test on
➤ Hydrology
➤ Solid Waste and Waste Water Treatment
➤ Water Supply
➤ Steel Structure
➤ Soil Mechanics and Foundation
➤ Pollution (Air and Noise)
➤ Irrigation
➤ Fluid Mechanics and Hydraulics