Important points selected at the ends of ...
Que.
Important points selected at the ends of the chain lines to command the boundaries of the survey are called :
A.
Main stations
B.
Subsidiary stations
C.
Tie stations
D.
None of the above
Right Answer is :
✓ A. Main stations
⚑ Report
Views 👍 :1.7K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Bitumen grade 80/100 indicates that under the ...
➣ Limiting length of offset depends upon : ...
➣ While aligning a hill road with a ...
➣ Inclination of the needle to the horizontal ...
➣ For detecting whether a bitumen is cracked ...
➣ The best binder material to be used ...
➣ On a right angled road inter-section with ...
➣ The main difference between optical square and ...
➣ The tie line is run throught the ...
➣ If average centre to centre spacing of ...
❖ Take a qick MCQ Test on
➤ Irrigation
➤ Concrete Technology
➤ Solid Waste and Waste Water Treatment
➤ Miscellaneous
➤ Hydrology
➤ Fluid Mechanics and Hydraulics
➤ Surveying
➤ Water Supply