Important points selected at the ends of ...
Que.
Important points selected at the ends of the chain lines to command the boundaries of the survey are called :
A.
Main stations
B.
Subsidiary stations
C.
Tie stations
D.
None of the above
Right Answer is :
✓ A. Main stations
⚑ Report
Views 👍 :1.6K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Which of the following is taken into ...
➣ On a right angle road inter-section with ...
➣ Shift of the transition curve of radius ...
➣ Positive error is caused if : ...
➣ A river is an obstacle to : ...
➣ The best binder material to be used ...
➣ Invar tapes are made of an alloy ...
➣ With regards to traversing : ...
➣ Maximum allowable limit upto that a measurement ...
➣ On a horizontal curve, if the pavement ...
❖ Take a qick MCQ Test on
➤ Water Supply
➤ Concrete Structure
➤ Surveying
➤ Strength of Material
➤ Building Material
➤ Pollution (Air and Noise)
➤ Transportation Engineering
➤ Soil Mechanics and Foundation