Que.
Important points selected at the ends of the chain lines to command the boundaries of the survey are called :
A.
Main stations
B.
Subsidiary stations
C.
Tie stations
D.
None of the above
Right Answer is :
✓ A. Main stations
⚑ Report
Views 👍 :1.5K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Which of the following is taken into ...
➣ Duirnal variation depends upon : ...
➣ What is the mechanical widening required for ...
➣ With increase in speed of the traffic ...
➣ Quadrantal system confines the user to measure ...
➣ Gravity model is used in transportation planning ...
➣ Most probable value of an observed quantity ...
➣ With regards to traversing : ...
➣ A building is an obstacles to : ...
➣ Invar tapes are made of an alloy ...
❖ Take a qick MCQ Test on
➤ Irrigation
➤ Water Supply
➤ Pollution (Air and Noise)
➤ Soil Mechanics and Foundation
➤ Transportation Engineering
➤ Solid Waste and Waste Water Treatment
➤ Strength of Material
➤ Hydrology