Que.
Important points selected at the ends of the chain lines to command the boundaries of the survey are called :
A.
Main stations
B.
Subsidiary stations
C.
Tie stations
D.
None of the above
Right Answer is :
✓ A. Main stations
⚑ Report
Views 👍 :1.3K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ For design, that length of transition curve ...
➣ Dip of the needle : ...
➣ During chaining along straight line,the leader of ...
➣ Obstacle to ranging but not chaining is ...
➣ For detecting whether a bitumen is cracked ...
➣ The best binder material to be used ...
➣ 30th highest hour volumes is : ...
➣ Errors which remain after mistakes and systematic ...
➣ In which of the following types of ...
➣ Open cross staff is used for setting ...
❖ Take a qick MCQ Test on
➤ Strength of Material
➤ Concrete Technology
➤ Water Supply
➤ Pollution (Air and Noise)
➤ Transportation Engineering
➤ Hydrology
➤ Irrigation
➤ Miscellaneous