Que.
Important points selected at the ends of the chain lines to command the boundaries of the survey are called :
A.
Main stations
B.
Subsidiary stations
C.
Tie stations
D.
None of the above
Right Answer is :
✓ A. Main stations
⚑ Report
Views 👍 :1.9K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ The main difference between optical square and ...
➣ With referance to the Marshall mix design ...
➣ While aligning a hill road with a ...
➣ The best binder material to be used ...
➣ In soil stabilisation : ...
➣ For detecting whether a bitumen is cracked ...
➣ Maximum allowable limit upto that a measurement ...
➣ Compensating errors in chaining are : ...
➣ Chain surveying is used for : ...
➣ If a vehicle travelling at 40 kmph ...
❖ Take a qick MCQ Test on
➤ Solid Waste and Waste Water Treatment
➤ Miscellaneous
➤ Concrete Structure
➤ Steel Structure
➤ Hydrology
➤ Strength of Material
➤ Soil Mechanics and Foundation
➤ Transportation Engineering