Que.
Important points selected at the ends of the chain lines to command the boundaries of the survey are called :
A.
Main stations
B.
Subsidiary stations
C.
Tie stations
D.
None of the above
Right Answer is :
✓ A. Main stations
⚑ Report
Views 👍 :1.7K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Gravity model is used in transportation planning ...
➣ Which of the following is taken into ...
➣ A 30m chain was found to be ...
➣ In compass surtveying : ...
➣ With increase in speed of the traffic ...
➣ Prismatic compass and surveyor's compass respectively given ...
➣ A field is measured with a 1.0 ...
➣ Invar tapes are made of an alloy ...
➣ The effect of grade on safe overtaking ...
➣ On a horizontal curve, if the pavement ...
❖ Take a qick MCQ Test on
➤ Miscellaneous
➤ Solid Waste and Waste Water Treatment
➤ Soil Mechanics and Foundation
➤ Concrete Structure
➤ Concrete Technology
➤ Fluid Mechanics and Hydraulics
➤ Steel Structure
➤ Pollution (Air and Noise)