Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.8K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ In which of the following types of ...
➣ Metallic tapes are made of : ...
➣ In a braking test, a vehicle travelling ...
➣ For detecting whether a bitumen is cracked ...
➣ Inclination of the needle to the horizontal ...
➣ The chain length which is not the ...
➣ In which of the following traffic signal ...
➣ A 30m chain was found to be ...
➣ Number of links in a 30 m ...
➣ Clearance distance or set back distance required ...
❖ Take a qick MCQ Test on
➤ Pollution (Air and Noise)
➤ Solid Waste and Waste Water Treatment
➤ Concrete Structure
➤ Irrigation
➤ Miscellaneous
➤ Hydrology
➤ Strength of Material
➤ Concrete Technology