The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.9K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Most probable value of an observed quantity ...
➣ In compass surtveying : ...
➣ If a vehicle travelling at 40 kmph ...
➣ On a horizontal curve, if the pavement ...
➣ If ruling gradients is 1 in 20 ...
➣ A vehicle moving at 40 kmph speed ...
➣ If in a Dorry abrasion test the ...
➣ Bitumen grade 80/100 indicates that under the ...
➣ Normal tension is that pull which : ...
➣ Length of a vehicle affects : ...
❖ Take a qick MCQ Test on
➤ Soil Mechanics and Foundation
➤ Solid Waste and Waste Water Treatment
➤ Steel Structure
➤ Concrete Technology
➤ Fluid Mechanics and Hydraulics
➤ Strength of Material
➤ Irrigation
➤ Transportation Engineering