The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.7K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ The position of point can be fixed ...
➣ Dip of the needle : ...
➣ Errors which remain after mistakes and systematic ...
➣ On a horizontal curve, if the pavement ...
➣ While aligning a hill road with a ...
➣ Which of the following statement (s) is/are ...
➣ With increase in speed of the traffic ...
➣ In a prismatic compass : ...
➣ Most probable value of an observed quantity ...
➣ On the right angled road inter-section with ...
❖ Take a qick MCQ Test on
➤ Irrigation
➤ Miscellaneous
➤ Hydrology
➤ Strength of Material
➤ Fluid Mechanics and Hydraulics
➤ Soil Mechanics and Foundation
➤ Concrete Structure
➤ Building Material