The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.9K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ In which of the following types of ...
➣ Method of offset laying involving minimum measurement ...
➣ In a prismatic compass : ...
➣ Maximum allowable limit upto that a measurement ...
➣ A negative declination shows the magnetic meridian ...
➣ A rotary will be more suitable than ...
➣ Open cross staff is used for setting ...
➣ Prismatic compass and surveyor's compass respectively given ...
➣ The main difference between optical square and ...
➣ In a closed traverse : ...
❖ Take a qick MCQ Test on
➤ Concrete Structure
➤ Transportation Engineering
➤ Pollution (Air and Noise)
➤ Steel Structure
➤ Concrete Technology
➤ Water Supply
➤ Building Material
➤ Surveying