The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.9K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ A river is an obstacle to : ...
➣ In which of the following types of ...
➣ A vehicle moving at 40 kmph speed ...
➣ When speed of traffic flow becomes zero, ...
➣ Which of the following is taken into ...
➣ A 30m chain was found to be ...
➣ If ruling gradients is 1 in 20 ...
➣ During chaining along straight line,the leader of ...
➣ In compass surtveying : ...
➣ Method of offset laying involving minimum measurement ...
❖ Take a qick MCQ Test on
➤ Transportation Engineering
➤ Irrigation
➤ Miscellaneous
➤ Soil Mechanics and Foundation
➤ Solid Waste and Waste Water Treatment
➤ Building Material
➤ Surveying
➤ Concrete Structure