The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.7K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ A field is measured with a 1.0 ...
➣ With referance to the Marshall mix design ...
➣ If free mean speed on a roadway ...
➣ Maximum allowable limit upto that a measurement ...
➣ Number of links in a 30 m ...
➣ When speed of traffic flow becomes zero, ...
➣ Quadrantal system confines the user to measure ...
➣ A building is an obstacles to : ...
➣ In which of the following traffic signal ...
➣ In a closed traverse : ...
❖ Take a qick MCQ Test on
➤ Pollution (Air and Noise)
➤ Water Supply
➤ Hydrology
➤ Transportation Engineering
➤ Surveying
➤ Steel Structure
➤ Solid Waste and Waste Water Treatment
➤ Miscellaneous