The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.9K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Errors which remain after mistakes and systematic ...
➣ Permissible limits of error in chaining of ...
➣ What is the psychological widening of pavement ...
➣ On a right angled road inter-section with ...
➣ Number of links in a 30 m ...
➣ Chain surveying is used for : ...
➣ Chainage is the distance measured : ...
➣ In desire line diagram : ...
➣ The best binder material to be used ...
➣ Prismatic compass and surveyor's compass respectively given ...
❖ Take a qick MCQ Test on
➤ Concrete Technology
➤ Building Material
➤ Fluid Mechanics and Hydraulics
➤ Irrigation
➤ Water Supply
➤ Soil Mechanics and Foundation
➤ Steel Structure
➤ Pollution (Air and Noise)