The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.7K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ If ruling gradients is 1 in 20 ...
➣ On a horizontal curve, if the pavement ...
➣ Negative errors are caused in chain, when ...
➣ What is the mechanical widening required for ...
➣ The tie line is run throught the ...
➣ The closing error in a traverse is ...
➣ Which of the following is taken into ...
➣ Invar tapes are made of an alloy ...
➣ Duirnal variation depends upon : ...
➣ The sag correction is always : ...
❖ Take a qick MCQ Test on
➤ Strength of Material
➤ Pollution (Air and Noise)
➤ Solid Waste and Waste Water Treatment
➤ Soil Mechanics and Foundation
➤ Fluid Mechanics and Hydraulics
➤ Concrete Structure
➤ Hydrology
➤ Surveying