The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.8K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ For design, that length of transition curve ...
➣ Which of the following is taken into ...
➣ Important points selected at the ends of ...
➣ Inclination of the needle to the horizontal ...
➣ Chain surveying is used for : ...
➣ The position of point can be fixed ...
➣ The main difference between optical square and ...
➣ Negative errors are caused in chain, when ...
➣ A field is measured with a 1.0 ...
➣ As per IRG-recommendation, the average level of ...
❖ Take a qick MCQ Test on
➤ Hydrology
➤ Water Supply
➤ Transportation Engineering
➤ Surveying
➤ Steel Structure
➤ Concrete Structure
➤ Irrigation
➤ Soil Mechanics and Foundation