The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.9K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ The main difference between optical square and ...
➣ In which of the following types of ...
➣ The chain length which is not the ...
➣ In desire line diagram : ...
➣ True meridians : ...
➣ In which of the following traffic signal ...
➣ The entrance and exit curves of a ...
➣ When speed of traffic flow becomes zero, ...
➣ Secular variation is important is important factor ...
➣ The optical square is based on the ...
❖ Take a qick MCQ Test on
➤ Surveying
➤ Miscellaneous
➤ Pollution (Air and Noise)
➤ Water Supply
➤ Solid Waste and Waste Water Treatment
➤ Hydrology
➤ Building Material
➤ Transportation Engineering