The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.9K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ With regards to traversing : ...
➣ On the right angled road inter-section with ...
➣ With increase in speed of the traffic ...
➣ If free mean speed on a roadway ...
➣ In a closed traverse : ...
➣ What is the mechanical widening required for ...
➣ Secular variation is important is important factor ...
➣ If a vehicle travelling at 40 kmph ...
➣ Important points selected at the ends of ...
➣ In a braking test, a vehicle travelling ...
❖ Take a qick MCQ Test on
➤ Pollution (Air and Noise)
➤ Concrete Structure
➤ Strength of Material
➤ Solid Waste and Waste Water Treatment
➤ Concrete Technology
➤ Water Supply
➤ Surveying
➤ Miscellaneous