The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.9K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ A 30m chain was found to be ...
➣ Chainage is the distance measured : ...
➣ For a constant value of co-efficient of ...
➣ What is the off-tracking of a vehicle ...
➣ The entrance and exit curves of a ...
➣ During chaining along straight line,the leader of ...
➣ Length of transition curve for design speed ...
➣ Dip of the needle : ...
➣ In survey works declinations varies from time ...
➣ With referance to the Marshall mix design ...
❖ Take a qick MCQ Test on
➤ Strength of Material
➤ Surveying
➤ Building Material
➤ Fluid Mechanics and Hydraulics
➤ Solid Waste and Waste Water Treatment
➤ Irrigation
➤ Steel Structure
➤ Water Supply