The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.9K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ If free mean speed on a roadway ...
➣ Compensating errors in chaining are : ...
➣ Metallic tapes are made of : ...
➣ Which of the following statements is/are correct ...
➣ With increase in speed of the traffic ...
➣ Prismatic compass and surveyor's compass respectively given ...
➣ Which of the following statement (s) is/are ...
➣ The effect of grade on safe overtaking ...
➣ Obstacle to ranging but not chaining is ...
➣ A rotary will be more suitable than ...
❖ Take a qick MCQ Test on
➤ Water Supply
➤ Concrete Structure
➤ Miscellaneous
➤ Soil Mechanics and Foundation
➤ Hydrology
➤ Strength of Material
➤ Pollution (Air and Noise)
➤ Concrete Technology