An irrigation canal is to be designed ...
Que.
An irrigation canal is to be designed to deliver 8.3 cumecs to meet the peak Rabi demand of a total of 8000 hectares of cropped area. The estimated canal losses are 25 % of the head discharge . The duty an capacity of this will be :
A.
723.32 ha/cumecs
B.
800 ha/cumecs
C.
594.64 ha/cumecs
D.
694.34 ha/cumecs
Right Answer is :
✓ A. 723.32 ha/cumecs
⚑ Report
Views 👍 :3.0K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ If in mass curve, a demand line ...
➣ The value of Sodium Absorption Ratio for ...
➣ What is the evaporation, if 4.75 litre ...
➣ The statement "ordinate of the direct runoff ...
➣ On suitable foundation, the earthen dam can ...
➣ If base period for a particular crop ...
➣ The based period of a 6 h ...
➣ The amount of irrigation water required to ...
➣ Out of 150 cm of water pumped ...
➣ What is the evaporation, if 4.75 litre ...
❖ Take a qick MCQ Test on
➤ Soil Mechanics and Foundation
➤ Transportation Engineering
➤ Surveying
➤ Water Supply
➤ Miscellaneous
➤ Pollution (Air and Noise)
➤ Steel Structure
➤ Fluid Mechanics and Hydraulics