Que.
Important points selected at the ends of the chain lines to command the boundaries of the survey are called :
A.
Main stations
B.
Subsidiary stations
C.
Tie stations
D.
None of the above
Right Answer is :
✓ A. Main stations
⚑ Report
Views 👍 :1.3K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Length of transition curve for design speed ...
➣ Prismatic compass and surveyor's compass respectively given ...
➣ With referance to the Marshall mix design ...
➣ As per IRG-recommendation, the average level of ...
➣ Chainage is the distance measured : ...
➣ A vehicle moving at 40 kmph speed ...
➣ In a closed traverse : ...
➣ If free mean speed on a roadway ...
➣ On a right angled road inter-section with ...
➣ Chain surveying is used for : ...
❖ Take a qick MCQ Test on
➤ Hydrology
➤ Building Material
➤ Water Supply
➤ Fluid Mechanics and Hydraulics
➤ Surveying
➤ Miscellaneous
➤ Solid Waste and Waste Water Treatment
➤ Concrete Structure