Important points selected at the ends of the chain lines to command the boundaries of the survey are called :
A.
Main stations
B.
Subsidiary stations
C.
Tie stations
D.
None of the above
Right Answer is :
✓ A. Main stations
⚑ Report
Views 👍 :1.4K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ On a right angle road inter-section with ...
➣ 30th highest hour volumes is : ...
➣ Clearance distance or set back distance required ...
➣ What is the psychological widening of pavement ...
➣ A negative declination shows the magnetic meridian ...
➣ In which of the following traffic signal ...
➣ Chainage is the distance measured : ...
➣ Length of summit curve for a stopping ...
➣ In a prismatic compass : ...
➣ During chaining along straight line,the leader of ...
❖ Take a qick MCQ Test on
➤ Fluid Mechanics and Hydraulics
➤ Pollution (Air and Noise)
➤ Hydrology
➤ Concrete Technology
➤ Solid Waste and Waste Water Treatment
➤ Miscellaneous
➤ Water Supply
➤ Strength of Material