The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.9K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Method of offset laying involving minimum measurement ...
➣ A vehicle moving at 40 kmph speed ...
➣ Normal tension is that pull which : ...
➣ Chainage is the distance measured : ...
➣ On a right angle road inter-section with ...
➣ Maximum allowable limit upto that a measurement ...
➣ On a horizontal curve, if the pavement ...
➣ A negative declination shows the magnetic meridian ...
➣ While aligning a hill road with a ...
➣ Which of the following statement (s) is/are ...
❖ Take a qick MCQ Test on
➤ Surveying
➤ Solid Waste and Waste Water Treatment
➤ Concrete Technology
➤ Transportation Engineering
➤ Steel Structure
➤ Strength of Material
➤ Hydrology
➤ Pollution (Air and Noise)