Que.
Important points selected at the ends of the chain lines to command the boundaries of the survey are called :
A.
Main stations
B.
Subsidiary stations
C.
Tie stations
D.
None of the above
Right Answer is :
✓ A. Main stations
⚑ Report
Views 👍 :1.3K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ A negative declination shows the magnetic meridian ...
➣ Obstacle to ranging but not chaining is ...
➣ Clearance distance or set back distance required ...
➣ In a prismatic compass : ...
➣ Number of links in a 30 m ...
➣ Chainage is the distance measured : ...
➣ Normal tension is that pull which : ...
➣ On a horizontal curve, if the pavement ...
➣ In soil stabilisation : ...
➣ With referance to the Marshall mix design ...
❖ Take a qick MCQ Test on
➤ Soil Mechanics and Foundation
➤ Irrigation
➤ Water Supply
➤ Concrete Technology
➤ Transportation Engineering
➤ Fluid Mechanics and Hydraulics
➤ Building Material
➤ Miscellaneous