The tie line is run throught the ...
Que.
The tie line is run throught the survey to :
A.
take off sets for detailed of nearby objects
B.
take details of nearby objects
C.
check accuracy of work
D.
none of these
Right Answer is :
✓ B. take details of nearby objects
⚑ Report
Views 👍 :1.7K
Share :
Copy ☍
✒ To discuss this topic
Comment
✕ Cancel
➤ Post Comment
❖ Related Questions
➣ Obstacle to ranging but not chaining is ...
➣ If average centre to centre spacing of ...
➣ Bitumen grade 80/100 indicates that under the ...
➣ The tie line is run throught the ...
➣ On the right angled road inter-section with ...
➣ Errors which remain after mistakes and systematic ...
➣ Limiting length of offset depends upon : ...
➣ Negative errors are caused in chain, when ...
➣ With increase in speed of the traffic ...
➣ In a braking test, a vehicle travelling ...
❖ Take a qick MCQ Test on
➤ Hydrology
➤ Solid Waste and Waste Water Treatment
➤ Strength of Material
➤ Miscellaneous
➤ Concrete Technology
➤ Surveying
➤ Soil Mechanics and Foundation
➤ Irrigation